Miami Black-owned businesses seek relief over delayed water infrastructure project

Miami-Dade County approved a 1,000-day project extension and an additional $5.41 million in funding, bringing the project’s estimated total cost to about $12.66 million. The Black Collective is calling for an independent economic-loss analysis and compensation for affected businesses. The dispute shows how prolonged public infrastructure work can threaten the revenue and viability of Black-owned businesses in historically Black commercial corridors.